Construction progress
Construction progress
Complex
Tower 1
Tower 2
Tower 3
Construction start
I quarter 2017
II quarter 2018
II quarter 2019
Construction end
III quarter 2020
II quarter 2022
II quarter 2023
First Tower put into operation
The opportunity to touch the future is getting closer!
Landscaping is in full swing
Taryan Towers are the city's new architectural magnet
Interior works and landscaping of the First Tower
The First Tower is getting closer to completion
The glazing of the facade of the Second Tower has begun
Installation of decorative lighting
We continue to build the future we want to live in
Installation of Swiss Schindler elevators
Roof of the First Tower
There is facade and monolithic works continue
The process of creating Taryan Towers
Installation of ventilation systems is underway in the Second Tower
5400 m2 of double-glazed windows were installed and 8 600 m2 of facade systems were prepared for glazing
Installation of internal engineering systems in the first tower
3900 sq.m of glass and 6387 sq.m of aluminum facade system installed
The 13th floor of the second tower is under construction
30 floor of 1th tower is under construction
3 floor of 2th tower is under construction
July 2018 results
The construction of the 5th floor of the 1st tower was complited
The construction of the 4th floor of the 1st tower was complited
The construction of the 3rd floor of the 1st tower was complited
The brickwork of the minus floors was started, the construction of the electrical networks of the building started
The construction of the 2nd floor of the 1st tower was complited
The construction of the 1st floor of the 1st tower was complited
The construction of the -1st floor of the 1st tower was complited
The constraction of stair flights of the 1st tower was completed
The construction of the -2nd floor of the 1st tower was complited
The construction of the -3rd floor of the 1st tower was complited
The grillage unit of the apartment house was completed
The construction of the grillage unit of the stylobate was complited.
The pile field was completed under the part of the stylobate part and the apartment house of the 1st tower
Building yard preparation completed