Project work
- Taryan Towers
- About the Complex
-
Construction progress


Construction progress
Complex
Tower 1
Tower 2
Tower 3
Construction start
I quarter 2017
II quarter 2018
II quarter 2019
Construction end
III quarter 2020
II quarter 2022
II quarter 2023

First Tower put into operation

The opportunity to touch the future is getting closer!

Landscaping is in full swing

Taryan Towers are the city's new architectural magnet

Interior works and landscaping of the First Tower

The First Tower is getting closer to completion

The glazing of the facade of the Second Tower has begun

Installation of decorative lighting

We continue to build the future we want to live in

Installation of Swiss Schindler elevators

Roof of the First Tower

There is facade and monolithic works continue

The process of creating Taryan Towers

Installation of ventilation systems is underway in the Second Tower

5400 m2 of double-glazed windows were installed and 8 600 m2 of facade systems were prepared for glazing

Installation of internal engineering systems in the first tower

3900 sq.m of glass and 6387 sq.m of aluminum facade system installed

The 13th floor of the second tower is under construction









30 floor of 1th tower is under construction

3 floor of 2th tower is under construction










July 2018 results










The construction of the 5th floor of the 1st tower was complited

The construction of the 4th floor of the 1st tower was complited

The construction of the 3rd floor of the 1st tower was complited

The brickwork of the minus floors was started, the construction of the electrical networks of the building started

The construction of the 2nd floor of the 1st tower was complited

The construction of the 1st floor of the 1st tower was complited

The construction of the -1st floor of the 1st tower was complited

The constraction of stair flights of the 1st tower was completed

The construction of the -2nd floor of the 1st tower was complited

The construction of the -3rd floor of the 1st tower was complited

The grillage unit of the apartment house was completed

The construction of the grillage unit of the stylobate was complited.

The pile field was completed under the part of the stylobate part and the apartment house of the 1st tower

Building yard preparation completed
Drag and drop